_______ economic system is prevailing in Pakistan:

(A) Mixed economic system
(B) Capitalistic economic system
(C) Socialistic economic system
(D) Traditional economic system

Answer: (A) Mixed economic system
Mixed economic system is prevailing in Pakistan.

If Schedule performance index (SPI) is 1, it means:

(A) you are over budget
(B) the project is progressing exactly as planned
(C) the project is running behind schedule
(D) None of these

Answer: (B) the project is progressing exactly as planned
If Schedule performance index (SPI) is 1, it means the project is progressing exactly as planned.